Bayer Butyl II – Halogenation Unit

·        The Bayer Butyl II Capacity Increase project was a major expansion at the Butyl site.

·        We supplied and installed two packaged rooftop units and three make up air units.

·        Two large capacity utility set fans were required for process exhaust and had to be coated with an Eisenheiss coating.

·        The ductwork for the process exhaust was Fibre Reinforced Plastic which we supplied and installed.

·        Six steam unit heaters were required to heat the railcar area.

·        In addition to the FRP ductwork there was 3600 lbs of galvanized ductwork and some spiral.

·        Our scope also included all plumbing, steam piping, and process piping.

Bayer Substation 19 & North MCC

·        This project involved the construction of a new MCC building and a substation.

·        The MCC building required three wall mount Liebert A/C units complete with electric heaters.

·        The Substation was heated and cooled using a packaged rooftop unit.

Bayer Central Change Facility

·        Built in 1997 this building is the main men’s and women’s change facility for the Bayer site.

·        This large scale project involved steam and hot water systems, below grade and above grade plumbing, and drainage.

·        The H.V.A.C. systems required 12,000 lbs of ductwork.